What a stiffened raft slab is
A stiffened raft is a floor slab with deeper beams cast into it: an edge beam all the way round and, on most sites, internal beams across the middle. The slab, the beams and any pads under heavy points are poured in one go.
So the concrete is the slab plus the parts of the beams that go below it. For the 12x10m example that is 12 m³ of slab and 3.85 m³ of edge beam.
How the edge beam corners are counted
Adding up the four sides of the edge beam counts each corner twice. The calculator instead takes the band inside the outline, so every corner is counted once. For the example that is 0.11 m³ less than adding the sides up.
The same holds for L and U shaped houses with square corners. Where internal beams cross, enter the number of crossings and the overlap is taken off once each. Sloped beam sides use the width halfway down.
Waffle pod slab volume
A waffle pod slab sits on polystyrene blocks laid on the ground, with ribs between them and a topping over them. The concrete is the whole depth minus the pods. On the same house with 225mm pods and an 85mm topping, 63 full pods leave 20.36 m³, against 37.2 m³ if the slab were solid to that depth.
Ordered as ready-mix with 10% extra, that waffle slab is 22.4 m³.
| Pod | Height | Plan area | Block volume |
|---|---|---|---|
| 1090x1090mm | 150mm | 1.19 m² | 0.178 m³ |
| 1090x1090mm | 175mm | 1.19 m² | 0.208 m³ |
| 1090x1090mm | 225mm | 1.19 m² | 0.267 m³ |
| 1090x1090mm | 300mm | 1.19 m² | 0.356 m³ |
| 1090x1090mm | 375mm | 1.19 m² | 0.446 m³ |
Why the pod count comes from your plans
Pod layouts depend on the rib width, the edge setback and where beams and set-downs fall, so two houses of the same area can take different numbers of pods. The calculator does not guess the count: type the full pods shown on your plans, and the area of any cut pods.
Open or moulded pods hold less than a solid block of the same size. For those, choose Other pod and type the void volume from the supplier, or the answer will be short.
What the calculator leaves to your engineer
Wall thickenings, garage step-down beams and deeper edges from your drawing go in as extra runs, each as length × width halfway down × depth below the slab, and piers under the beams go in as a count. Beyond that the tool stops and the drawing takes over.
- Beam depths and slab thickness by site class: your engineer sizes them to AS 2870, and the calculator only adds up what the drawing shows.
- Set-down recesses for wet areas: a few hundredths of a cubic metre a metre, left out.
- Steel is not deducted: mesh and bar take well under 1% of the volume.
- Over-excavation and an uneven base: measured on site, not from a plan, so order with the CCAA 10% allowance and the concreter's judgement.
- Classes E and P and filled sites, edge beams over 1.5m deep, slabs over 30m long: engineering advice territory.
Ordering ready-mix for a house slab
Cement Concrete and Aggregates Australia (CCAA) advises ordering about 10% more than the exact volume and rounding up, because premix is batched in 0.2 m³ steps. Suppliers often charge a small load as if it were a bigger one, so a top-up truck is poor value: order enough the first time.
Questions
For a stiffened raft, add the slab to the parts of the beams below it. A 12x10m raft with a 100mm slab and 300x300mm edge beams is about 15.85 m³ before any extra.
Multiply the slab area by the pod height plus topping, then take off the pods: number of pods × pod length × width × height. Add any edge beam that goes deeper than the pods.
The common solid pods are 1090x1090mm in plan, in heights of 150, 175, 225, 300 and 375mm. The ribs between them are 100 or 110mm wide.
Yes. The pod count changes with the layout, so take it from your slab plans. Cut pods are entered as a total area.
No. Slab thickness, beam sizes and pod heights come from your engineer. The calculator turns those sizes into a concrete quantity.
Goes with this job
Disclaimer
This calculator gives estimates from the sizes you enter, using manufacturers' published figures and standard geometry. It is not engineering or design advice. Footing, slab and beam sizes must come from your plans or engineer. Allow for site conditions, spillage and uneven ground. Check quantities with your supplier before ordering. Allmat accepts no responsibility for decisions made using these estimates.
Sources
- CCAA: Guide to Residential Floors (T49)
- CCAA: Ordering Premixed Concrete
- Foamex: StyroPod EPS waffle pods
- Polyfoam: waffle pods
- Allmat arithmetic (this calculator)
Last checked 5 October 2026.
Cite this page
Allmat, "House slab calculator: raft and waffle pod", https://allmat.com.au/concrete-calculator/house-slab, checked 5 October 2026.
